The homeowner walks into the kitchen you’re halfway through and says, “While you’re here, could you also move that outlet?” Or the general contractor calls to say the client wants a different window size, and can you price it today. Or you open a wall and find something nobody planned for.
The work itself is usually straightforward. The paperwork is where small jobs turn into arguments months later. A change order that exists only as a conversation is easy to remember differently. A signed one, sent the same day, is not.
Here are three common job-site situations, and how to handle the signing and sending from your phone without a trip back to the office. It isn’t legal advice. Your contract, local rules and, for anything contested, a lawyer who knows construction contracts are the authorities on what a change order needs to be binding.
What a useful change order contains
Before the scenarios, it helps to know what you’re trying to get signed. A change order doesn’t have to be long, but it should be specific. Most good ones include:
- Reference to the original contract, by date or job number, so it’s clear which agreement it changes
- A plain description of the change, specific enough that a stranger could tell what was added, removed or altered
- Price impact, as an added amount, a credit, or a basis such as time and materials, depending on what your contract allows
- Schedule impact, even if it’s “no change to completion date”
- Any changes to materials or specifications
- Date, names and signatures of the people authorized to agree to it
Many contracts include their own change order clause, sometimes with a required form. Read yours. If it says changes must be approved by a particular person, a homeowner’s spouse agreeing in passing may not be enough.
Keep a blank change order template on your phone as a PDF. Filling in a template on site is much faster than writing one from scratch while the client waits.
Scenario one: the homeowner asks for something extra
You’re on site, the client is standing next to you, and they want more work done.
- Describe the change in your own words, out loud, and check that you both mean the same thing. “Move the outlet from the left of the sink to the right, about 18 inches, patch and paint the old location.”
- Price it. If you can’t price it on the spot, say so and agree on when you will. Don’t start the extra work until the price is agreed and signed.
- Fill in the change order on your phone. Open your template, type the description, price and schedule impact.
- Hand the phone to the client to read it. Add your signature if your contract allows on-screen signatures, and have the client sign in whatever way the contract allows, such as on a printed copy. A signature added on screen may not be accepted for every contract, so check before you rely on it.
- Send a copy to wherever it needs to go, and give the client their copy.
With an app like FaxLane, you can import the template, add the text and your own signature, and then fax it to your own office line, the client’s home office or a general contractor, from the kitchen you’re standing in. Every page is visible for review before anything is sent, which is a good moment to hand the phone back to the client for one last look.
Scenario two: the general contractor needs your signature on their form
On larger jobs, you’re often a subcontractor, and the general contractor issues the change orders on their own form. They might email it to you as a PDF and ask for it back by fax before the end of the day.
- Read the whole form, not just the price line. GC forms sometimes include language about waiving claims for delays or additional costs related to the change. If that wording concerns you, raise it before signing.
- Check that the description matches what you priced. If it’s vaguer or broader, ask for it to be tightened.
- Sign on your phone, add the date, and initial any pages that ask for it.
- Attach your backup if the GC wants it, such as your pricing sheet or a photo of the condition that triggered the change. Photos can be added as pages in the same packet.
- Fax it back with a cover page that names the project, the change order number, and your company.
Don’t skip the cover page. A GC’s office may be processing change orders from a dozen subs on a dozen projects. “Lakeshore Clinic renovation, CO #7, electrical, 3 pages” gets filed correctly. A bare signature page might not.
Scenario three: you find something nobody planned for
You open a wall and find rot, old wiring, or a pipe where the drawings say there isn’t one. Work can’t continue as planned.
- Stop and document. Take clear photos of the condition, ideally with something for scale. Note the time and date.
- Tell the client or GC right away, by phone, and follow up in writing.
- Prepare a change order or a notice, depending on what your contract requires. Some contracts require a notice of a concealed or unexpected condition within a set time; read yours.
- Include the photos as pages in the packet, with a short description of each.
- Send it the same day, and keep the delivery receipt.
Here the delivery receipt is especially useful. It shows the date and time the receiving machine accepted your fax, which helps if there’s later a question about when you raised the issue. It doesn’t show that anyone read it, so follow up with a call.
Making it work in the field
Job sites aren’t offices. A few things make phone-based paperwork go more smoothly.
Scan on a flat, clean surface. If you’re scanning a paper form or a printed drawing with markups, put it on a sheet of plywood or a clipboard, not on your knee. Edge detection works best with a clear contrast between the page and what’s under it. Use the clean-up step, then zoom in to check that pencil marks and stamps are readable.
Keep the phone charged. Obvious, but a dead phone at the moment the client is ready to sign is how verbal agreements happen.
Signal can be patchy. Basements, steel-framed buildings and rural sites can all have weak coverage. Prepare and sign everything on site, and if the fax won’t go through, step outside or send it from the truck. If a send fails, you can retry once you have a better connection.
Check the number. The fax number for a GC’s project office may differ from their main office. Use the one they gave you for this project, and confirm it before sending. A fax can’t be recalled once it’s delivered.
Keep the paper trail together
For each job, keep the original contract, every change order in order, the delivery receipts, and any photos or notices. Name them consistently, like “Job 2417 CO-03 outlet relocation,” so they’re easy to find months later.
At the end of the job, when the final invoice goes out, this file is what lets you show exactly how the price moved from the original contract to the total. A signed, dated change order is much harder to argue with than anyone’s memory of a conversation.
Quick answers
Should I get a change order signed before doing extra work?
It's widely considered good practice to get changes agreed in writing before starting the extra work, so the scope, price and timing are clear to both sides. Check what your contract says about changes, since many contracts set out a specific process. For questions about enforceability, talk to a lawyer familiar with construction contracts where you work.
Can a client sign a change order on my phone at the job site?
Often, yes, if your contract and the client allow it. You can prepare the change order on your phone, have the client review it and sign in whatever form your contract allows, then send a copy by fax to whoever needs it, such as the client's office or a general contractor. Keep a copy and the delivery receipt with the job file.